Mason-Days, Rates and Attendance: A Simple Labor Tracking System
Labor is 25–35% of your construction cost and the easiest place to lose money. A simple mason-day system for tracking attendance, rates and payments in Nepal.
GharNaksa Team
Construction tracking for Nepal
Materials leave evidence — bags, bars, bills. Labor leaves nothing. A mason-day that was never worked looks exactly like one that was, once a week has passed. That is why labor, at 25–35% of a typical build cost, is the easiest place on a construction site to lose money without ever seeing it go.
The defense is a small daily ritual: count heads, note rates, log payments. Here is the system in full.
First, know what you are paying for
Nepali sites usually mix three arrangements, and each needs slightly different tracking:
- Daily-wage (jyala) — masons and helpers paid per day worked. Track attendance and the day rate. This is where the mason-day record lives.
- Piece-rate (thekka by quantity) — brickwork per thousand bricks, plaster per square foot. Track measured quantities, not days.
- Labor contract (labor thekka) — a fixed amount for a defined scope. Track advances against verified progress, never against promises.
The daily attendance record
Every evening, record four things — it takes two minutes:
- 1Who worked — by name or role: 3 masons, 5 helpers, 1 bar-bender.
- 2The rate for each role — mason 1,800, helper 1,000, whatever your site pays. Rates recorded daily catch quiet increases immediately.
- 3What they worked on — “second-floor brickwork,” “ground-floor plaster.” This connects cost to progress.
- 4Any advances paid — cash given today, to whom. Advances forgotten are the classic source of end-of-month disputes.
Where labor money leaks
- Ghost attendance. Eight workers billed, six on site. A daily head-count ends it — especially when the counter changes unpredictably.
- Rate creep. The rate agreed in Falgun is not the rate billed in Asar. Daily rate records make every change visible and datable.
- Double-paid advances. An advance paid in cash on Tuesday, forgotten by Saturday’s settlement, paid again. A written advance log pays for itself the first month.
- Idle days billed as worked. Rain days, material-shortage days, curing days. A log that says what was worked on makes idle days visible.
- Contractor and crew settling in private. When the owner’s record and the contractor’s record are the same shared record, the space for creative accounting disappears.
Connecting labor to progress
A labor log alone tells you what you spent. Combined with a daily site log and stage photos, it tells you what you got. Sixty mason-days on the first-floor slab is either fine or alarming depending on whether the slab is done — the pairing is the point. This is also the record your client abroad most wants to see next to the money they sent.
Doing it in GharNaksa
GharNaksa has a dedicated labor module: log attendance by role, set rates, record advances and payments, and see labor cost per stage next to your material spend. At settlement time, the running ledger replaces the argument — and the PDF export gives your crew and your client the same clean statement.